Progress Report on Shenzhen Major Projects (January-May 2022)
2022年1-5月深圳市重大项目进展情况
深圳市发展和改革委员会
fgw
This document reports the progress of Shenzhen's major projects for the first five months of 2022, detailing the total number of projects, investment amounts, and completion rates against annual plans.
Document Text
91 characters
2022年全市共安排重大项目883个,总投资约3.6万亿元,其中,建设(新建、续建)项目637个,年度计划投资2241.3亿元,1-5月完成投资1026.0亿元,完成进度45.8%。