How to Calculate Labor Costs for Secondary Transfer of Engineering Materials in Water Conservancy Project Cost Estimation?

水利工程造价编制过程中关于工程材料二次转运的人工费如何计取?

Issuer
Date
2023-08-07
Instrument
document
Cited by
0
This document provides an official interpretation on how to account for labor costs associated with the secondary transfer of engineering materials during the preparation of water conservancy project cost estimates. It clarifies the calculation method to guide practitioners.
Full text · 原文 131 字
当前位置:<br> 首页 > 政务公开 > 解读回应 > 回应关切<br> 水利工程造价编制过程中关于工程材料二次转运的人工费如何计取?<br> 来源:厅水利工程建设处<br> 发布时间:2023-08-07 10:53<br> 点击数:{{pvCount}}<br> |<br> |<br> |<br> <span