中国政策档案 Governance Archive HOLDINGS 191,422 · FONDS 70
Record · 中山市人民政府办公室 ACC. 2378268
中府函〔2024〕56号

Official Reply of Zhongshan Municipal People's Government on the Detailed Control Plan (2024) for Dengdu Industrial New City, TOD Comprehensive Development Project at Guzhen Station of Guangzhou-Zhuhai Intercity Railway

中山市人民政府关于广珠城轨古镇站TOD综合开发项目灯都产业新城控制性详细规划(2024)的批复

Issuer
中山市人民政府办公室
Date
2024-02-29 14:51:44
Instrument
reply
Cited by
0
This document approves the detailed control plan for the Dengdu Industrial New City TOD project at Guzhen Station, confirming its compliance with national and provincial urban planning laws and the Zhongshan territorial spatial master plan. It requires the Guzhen town government to strictly implement the plan and publicly release it within 20 working days.
Full text · 原文 424 字
古镇镇人民政府: 你镇《关于审批〈广珠城轨古镇站TOD综合开发项目灯都产业新城控制性详细规划〉成果的请示》(古府请〔2024〕2号)收悉。经研究,批复如下: 一、经审核,《广珠城轨古镇站TOD综合开发项目灯都产业新城控制性详细规划》的编制程序符合《中华人民共和国城乡规划法》《广东省城乡规划条例》《城市、镇控制性详细规划编制审批办法》《广东省控制性详细规划管理条例》相关要求,规划成果基本符合《中山市国土空间总体规划(2021-2035年)》要求。因此,原则同意《广珠城轨古镇站TOD综合开发项目灯都产业新城控制性详细规划》,规划成果命名为《广珠城轨古镇站TOD综合开发项目灯都产业新城控制性详细规划(2024)》(下称《控规》)。 二、你镇要加强对《控规》实施的指导、监督和检查工作,不得随意调整《控规》;确需调整的,必须按法定程序办理,确保《控规》的严格实施,并在《控规》获批之日起20个工作日内,向社会公布。中山市人民政府2024年2月23日