Reply from Pingshan District Housing and Construction Bureau to Representative Suggestion No. 20240124 at the Second Session of the Second District People's Congress

坪山区住房和建设局关于区二届人大四次会议第20240124号代表建议答复的函

Issuer
深圳市坪山区住房和建设局
Date
2024-09-06 16:05:45
Instrument
reply
Cited by
0
This document is a formal reply from the Pingshan District Housing and Construction Bureau to a representative's suggestion regarding the acceleration of road construction around Yanlan Hening residential community. It outlines coordination efforts and confirms that the community was delivered on April 3, 2024, with the southern road basically completed.
Full text · 原文 279 字
尊敬的吴思扬代表: 您提出的《关于加快推进燕澜和鸣小区周边道路建设的建议》(第20240124号)收悉。我局高度重视,经认真研究,现答复如下: 一、为推动燕澜和鸣项目实现顺利验收交付,我局已组织燕澜和鸣项目方及文慧路的建设、施工等相关参建单位召开验收协调会议,推进包括文慧路建设在内的燕澜和鸣小区相关验收工作。会议明确了工程建设计划和完成时限,要求各单位通力合作,确保燕澜和鸣小区平稳交付。 二、燕澜和鸣小区已于2024年4月3日顺利交付,南侧(文慧路)道路已基本建成(此道路将与天健和悦府项目一同验收),目前小区雨污水管已接入市政管网,可正常使用。 此函。