Progress Report on Shenzhen Major Projects (January-July 2024)
2024年1-7月深圳市重大项目进展情况
深圳市发展和改革委员会
fgw
This report provides an update on the progress of Shenzhen's major projects for the first seven months of 2024, detailing the number of projects, total investment, and completion rate of the annual investment plan.
Document Text
92 characters
2024年全市共安排重大项目859个,总投资约3.6万亿元,其中,建设(新建、续建)项目703个,年度计划投资2985.7亿元,1-7月完成投资2143.5亿元,投资进度率71.8%。