Record · 深圳市龙岗区人民政府 ACC. 11408050

Reply from Longgang District Construction Works Department on Proposal No. 202400006 of the Fourth Session of the Seventh District People's Congress

龙岗区建筑工务署关于区七届人大四次会议第20240006号建议答复的函

Issuer
深圳市龙岗区人民政府
Date
2024-07-04 15:31:34
Instrument
reply
Cited by
0
This document is a formal reply from the Longgang District Construction Works Department to three district-level people's congress representatives regarding their proposal to accelerate the construction of the second phase of Lilang Road. It outlines the project's history, current progress, and plans to complete design and begin construction within the year to address a long-standing road gap.
Full text · 原文 778 字
王舒、李智忠、张雪强人大代表: 你们在龙岗区七届人大四次会议的建议《关于推动李朗路二期工程的建议》(第20240006号)收悉,我署高度重视积极办理,现将有关情况函复如下: 一、建议涉我署项目基本情况 所提建议涉及我署负责建设的李朗路,该项目2009年1月立项,南起南湾街道田心路,北至平湖街道富安东路,城市次干路,红线宽30—35米,双向4—6车道,全长约3.4公里。 二、项目进展 受项目沿线各片区开发建设进度不一致、机荷高速、平南铁路、拆迁等影响,结合专家意见,项目分期分段实施。截至2022年,李朗路(田心路—友信路),李朗路(新木路—富康路)均已按规划完成建设并投入使用。 李朗路(友信路—新木路),此前受征拆及机荷高速改扩建项目设计不稳定影响,基本处于停滞状态,2023年在征拆工作推进顺利及机荷高速改扩建项目设计实施目标稳定情况下,我署重新启动了本段李朗路的前期工作。 目前,李朗路(友信路—新木路)已完成初步设计编制,已申报概算审核,现根据概算预审意见补充征求意见、完善设计等工作。 三、建议所提问题的回复 各位代表提出“建议区相关部门加快立项,全力推进启动李朗路二期建设,打通这条阻碍发展的“断头路”,李朗路二期建设将打通市民幸福出行的“最后一公里”,解决人民群众急、难、愁、盼的民生“痛点”。” 本项目2009年1月已整体立项,建议所提路段目前我署已进行概算申报,正在根据概算预审意见补充征求意见、完善设计,下一步我署将加快取得概算批复,开展施工图设计,争取年内动工建设,尽早打通该段“断头路”。 最后,感谢你们对现状问题的深入分析及所提的宝贵建议,希望你们继续建言献策、同时帮助我署协调解决建设过程出现的难题,共同推进项目建设。 特此函达。深圳市龙岗区建筑工务署2024年7月2日 (联系人:林杰扬,电话:0755-89551210)