Progress of Major Projects in Shenzhen, January-February 2023
2023年1-2月深圳市重大项目进展情况
深圳市发展和改革委员会
fgw
This document reports the investment progress of 841 major projects in Shenzhen for the first two months of 2023, with a total investment of approximately 3.6 trillion yuan and a completion rate of 9.0% of the annual plan.
Document Text
82 characters
2023年全市共安排重大项目841个,总投资约3.6万亿元,其中,建设项目594个,年度计划投资2813.5亿元,1-2月完成投资252.9亿元,完成进度9.0%。
Topics
infrastructure investment
project progress
urban development
Metadata
| Publisher | 深圳市发展和改革委员会 |
| Site | fgw |
| Date | 2023-03-28 10:06:01 |
| Category | report |
| Policy Area | 重大建设项目 |
| CMS Category | 重大建设项目 |